TCN Restores Kainji–Birnin Kebbi 330kV Transmission Line – THISDAYLIVE

TCN Restores Kainji–Birnin Kebbi 330kV Transmission Line – THISDAYLIVE


The Transmission Company of Nigeria (TCN) has announced that the 330kV Kainji–Birnin Kebbi Single Circuit Transmission Line, which was taken out of service following the collapse of Tower 367 on September 7, 2026, has been restored to service.

The line, according to the company, was restored after the erection of an Emergency Restoration System (ERS) tower at the tower location in Yauri.

“The restoration works involved dismantling and decommissioning the collapsed tower, aligning and preparing the conductors and skywire, erecting the ERS tower, and carrying out other associated works required to restore the line safely. TCN engineers worked round the clock to complete the works and return the line to service as quickly and safely as possible,” the company added. TCN said it appreciates the patience and understanding of electricity consumers in the affected areas throughout the period of the outage and remained committed to maintaining a stable and reliable transmission network.



Source link

Ruth Oyiza

Ruth Oyiza Zaccheaus is a news blogger, content creator, and microbiology researcher with a deep passion for keeping society informed. Through her work, she delivers timely, well-researched, and verifiable reporting on politics, public affairs, and health, with a strong commitment to accuracy, clarity, and responsible publishing. Drawing on her scientific background, Ruth brings a careful, evidence-based approach to every story, ensuring that readers receive information they can trust and understand. She believes that informed readers are empowered readers, and she is dedicated to bridging the gap between complex developments and the public. Ruth is currently an M.Sc. student at Kogi State University, Ayangba.

Leave a Comment

Your email address will not be published. Required fields are marked *